GROUNDTRAX CELLPAVE 50 PROVIDES A DURABLE, ALL-WEATHER SURFACE FOR NORTH WEALD MARKET

Groundtrax supplied 36,000m² of CellPave 50 cellular paving to transform North Weald Market in Essex, providing a durable, cost-effective ground reinforcement solution that improves accessibility and supports year-round market operations.
Project: North Weald Market
Location: North Weald Airfield, Essex
Date: November 2026

Client: Epping Forest District Council
Paving Contractor: Nigel McKie Limited (NML Paving)
Products Supplied: Groundtrax CellPave 50
Area: 36,000m²

 PROJECT OVERVIEW

North Weald Market, located at North Weald Airfield in Essex, required a durable ground reinforcement solution to improve conditions for traders, vehicles and visitors throughout the year.

Previously held on a grass field, the market experienced challenging ground conditions, becoming boggy during wet weather and hard and cracked during prolonged dry periods. This made the surface unpredictable and highlighted the need for a more reliable, long-term solution.

Epping Forest District Council commissioned the installation of 36,000m² of cellular paving to create a stable, practical surface capable of accommodating regular market traffic and improving accessibility for visitors.

THE CHALLENGE

Origin Green-tech's Groundtrax team was involved from the early planning stages, working with Epping Forest District Council to identify a suitable ground reinforcement solution for the site.

CellPave 50 was selected for its strength, durability and ability to provide a stable, reinforced surface capable of accommodating regular vehicle and pedestrian traffic.

The cellular paving system is designed to reinforce ground surfaces, distributing loads and helping to prevent rutting and surface deterioration. Its robust construction and proven load-bearing capabilities made it particularly suitable for the challenging ground conditions at North Weald Market.

Offering a cost-effective alternative to conventional hard surfacing, CellPave 50 provided a practical, long-term solution designed to improve accessibility and support the market's year-round operation.

THE INSTALLATION

Following the product specification, Groundtrax engaged NML Paving to undertake the installation of the cellular paving, they worked directly for Epping Forest District Council to deliver the extensive 36,000m² installation.

The scale of the installation required careful management by NML Paving to ensure the ground preparation and paving installation progressed efficiently.

IMPACT AND OUTCOME

The completed installation transformed the former grass field into a reinforced surface, providing a more dependable area for market operations throughout the year.

By addressing the challenges associated with the original ground conditions, the project has created a durable, long-term solution designed to accommodate regular vehicle movements while improving accessibility for traders and visitors.

The project demonstrates how the right ground reinforcement system, combined with effective planning and installation, can provide a practical and cost-effective alternative to conventional hard surfacing.

Nigel McKie, Director of NML Paving, commented, “CellPave 50 proved to be a great solution for the site, providing a strong and reliable surface. The installation went well and we were very pleased with the finished result.”

Nationwide Delivery
Nationwide Delivery
secure online payments
secure online payments
established over 30 years
established over 30 years
iso 9001 & 14001 certified
iso 9001 & 14001 certified
Newsletter Sign up Join Our
Mailing List